Project Description
Berolina-CIPP | Northern Beaches Council, NSW
The challenge
Downer PipeTech was engaged by Northern Beaches Council to undertake repairs and remediation works to stormwater infrastructure within a private property along the Manly waterfront.
Specific considerations that were sensitive to this site included the environmental management, the local penguin colony and the challenging waterfront access.
The full scope of works included community consultation and stakeholder management, CCTV investigation of pipelines, demolition of existing vertical structure, CIPP linings of the pipelines and reconstruction of the concrete vertical structure.
The solution
The Berolina-CIPP lining was undertaken using our UV cured Berolina liner which provides a 50-year design life with minimal loss of diameter.
The new concrete structure was built in line with construction principles similar to that of our Tunnelining concrete lining system.
The works were completed without incident and without any negative impact on the surrounding flora and fauna including Manly’s penguin population.
The outcome
Successful completion of this project has provided Northern Beaches Council with a fully remediated stormwater asset that will service the community into the foreseeable future and alleviate the concerns of the local residents related to any detrimental impact to their surrounding community and environment.